Building and Commissioning an Electrical Substation (TNB Contractors)

Introduction

The objective of the course is to provide theoretical and practical training regarding the process of building a Division Substation up to 22kV, from the procuring of the substation to successfully getting the substation on the grid. The focus will be 80% practical and 20% of theory and case studies. The course will refer to the latest manual and guidelines used by TNB on the building of substations.

This course is beneficial for those who are involved in the building and commissioning of a fully functioning substation as participants will learn how to do so correctly and safely.

TNB DISTRIBUTION (TNB Contractor)

Target Participant

ILSAS BANGI

Venue

5 DAYS

Duration

Objective

At the end of the course, participants will be able to:

  • Identify the types of substations and their main functions
  • Follow the civil specifications for the building of substations
  • Describe a substation’s site requirements and specifications
  • Perform the transportation and unloading of a substation according to the correct guidelines
  • Perform the installation of a substation’s major components according to the correct guidelines
  • Perform the testing of a substation’s major components according to the correct guidelines
  • Write a work completion report with the correct format

Agenda

Day 1

INTRODUCTION TO THE DIVISION ASSISTANCE BUILDING WORKS

  • Specification of the Substation Building
  • Preparation of Substation Main Equipment Site
  • Work of Transporting & Unloading Substation Equipment
Day 2

INSTALLATION OF RMU SWITCH TOOL

  • Types of RMU Switch Tools
  • Site Preparation and RMU Installation
  • RMU Testing & Assignment
  • Work to Dismantle RMU
  • Work On Installation of the Boiler
Day 3

INSTALLATION OF SWITCH TOOLS CIRCUIT BREAKER AND MODIFIERS

  • Provision of Installation Work Equipment and Safety Measures
  • Types of Circuit Breaker Types and Their Specifications
  • Site Preparation and a Circuit Breaker Installation
  • Development of Transformer Site
  • Installation of Transformers with Accessories
Day 4

INSTALLATION OF LOW VOLTAGE DISTRIBUTION BOARD

  • Preparation of Installation Work Equipment and Safety Measures
  • Site Preparation and PPVR Installation
  • Installation of AT Supply System
  • Battery Assembly

TESTING AND ASSIGNING CIRCUIT BREAKERS

  • Perform IR Testing, Continuity, CRT, Power Frequency Withstand Test & Vacuum Interrupter Test
  • Filling Test Format
Day 5

TESTING OF SWITCH TOOLS AND PPVR

  • Test Equipment Setup and Safety Measures
  • Perform IR Testing, Continuity, Winding Resistance & Turn Ratio for Variables
  • Testing and Managing the PPVR

SUBSTITUTION REFINERY WORK

  • Reorganization of Work Equipment

CASE STUDIES

What people say?

It was a perfect match seeing that i need to work on my confidence.I actually learnt more skills that is needed for me to be able to develop training programs.
Bodil Dahl
Ceo & Founder Crix
The course definitely helped in improving concepts. It would be great if you add more examples of templates for Training evaluation. This would help in creating better sheets in future. Thanks
Sonal Tyagi
Head Of Sales , Intel

Acknowledgement

Summary of Personal Data Protection Notice

This summary notice provides the key concepts of the Personal Data Protection Notice which applicable at Tenaga Nasional Berhad and our subsidiaries, which is available at our website.

Personal Data We May Collect & How We Collect It

We may collect your personal data including sensitive personal data such as personal information directly from you, your authorized representatives, third parties or from publicly resources. If you are a job applicant, employee or work for us, we shall provide a separate Notice to inform you how your personal data is used via our applicable platform.

Use of Personal Data Collected

We use your personal data to enable us to provide our services and matters related to it, send information on our services, for the purpose of audit and to comply with the regulatory obligations or industry codes.

With Whom We Share Your Personal Data

We disclose your personal data to the third parties located within or outside Malaysia who work on our behalf or help to provide our services.

If Personal Data Provided by You Is Incomplete

We may not be able provide you with our services for if the personal data given is incomplete.

Your Rights to Your Personal Data

You may request to access,correct and portability of your personal data held by us.

How Long We Will Keep Your Personal Data & How We Protect It

Your personal data will be retained to fulfil the purpose for which it is collected or to comply with legislation and internal requirements in which we will keep it safe.

Consent

By submitting your personal data, you consented to the processing of personal data as set out in this Notice.

Our Contact Details

TNB or its subsidiaries is committed to protecting your personal data. If you have questions or comments about TNB’s administration of personal data relating to electricity supply, please contact us at tnbcareline@tnb.com.my or 1-300-88-5454.

If you have any questions, comments or suggestions regarding this Policy, we would be glad to hear from you. Please contact our TNB Data Protection Officer at dpo@tnb.com.my

For more information, please download our full PDPA Notice here: